Project Type: CAISO meter replacements
Alta Wind 4 & 5 – Owned by Clearway Energy
Alta Wind 8 – Owned by Brookfield
Alta Wind 9 (Now Pinyon Pines II ) – Owned by BHE Renewables
Alta Wind 4 – CAISO meter replacement – 150 MW
Alta Wind 5 – Meter replacement – 150 MW
Alta Wind 8 – CAISO meter replacement – 150 MW
Alta Wind 9 – CAISO meter replacement- 150 MW
French Meadows – Meter replacement- 150 MW
Location: Various locations in California
Products/Services: Revenue meters at all locations
Trimark replaced the CAISO-certified revenue metering for each of the sites with the three separate resource owners. All four sites communicate through peer-to-peer functioning. Trimark worked with a third party programmer to program and install main and back-up meters at each of the wind sites.
Controller to Lead Trimark Accounting Team and Processes Folsom, CA, April 28, 2023 – Trimark Associates, Inc. (Trimark), the industry…
To our valued clients, You may have recently seen the following email from CAISO: You are receiving this notice as…
Folsom, CA, October 6, 2023 – Trimark has introduced cloud-based, Automatic Dispatch System (ADS) services to help small BESS and…
Project Type: PV generating facilities – over 50 sites Location: CA and MA Client/EPC: N/A Products/Services: Multi-year service agreement with…
Project Type: Automated Metering Infrastructure (AMI) Location: VA, MD, PA, NJ, CT and ME Client: Subcontractor to Weston; Client: Naval…
Need a SCADA system that optimizes revenue?
Need help meeting interconnection requirements?
Want to stay in the market and avoid fines?
Weʼve got you!
Get Started Today