Alta Wind 4, 5, 8, and 9

Project Type: CAISO meter replacements

Alta Wind 4 & 5 – Owned by Clearway Energy

Alta Wind 8 – Owned by Brookfield

Alta Wind 9 (Now Pinyon Pines II ) – Owned by BHE Renewables

Alta Wind 4 – CAISO meter replacement – 150 MW

Alta Wind 5 – Meter replacement – 150 MW

Alta Wind 8 – CAISO meter replacement – 150 MW

Alta Wind 9 – CAISO meter replacement- 150 MW

French Meadows – Meter replacement- 150 MW

Location: Various locations in California

Products/Services: Revenue meters at all locations

Trimark replaced the CAISO-certified revenue metering for each of the sites with the three separate resource owners. All four sites communicate through peer-to-peer functioning. Trimark worked with a third party programmer to program and install main and back-up meters at each of the wind sites.