Trimark Announces Realtime Monitoring of CAISO RIGs
Jul 06, 2022
Customers can receive alerts if an outage occurs and view details to expedite mitigation. Trimark Associates, Inc., the industry leader…
Expert insight helps lower your risk and reduce costs -- a direct benefit to your bottom line.
Better for the Owner! Better for the Integrator! Better for the Grid!
End-to-end guidance from experts who have guided over 900 resources to successful grid connection.
The Trimark Operations Center (TOC) helps you maintain compliance and ensure accurate data.
A Comprehensive Training Ecosystem for Power Industry Professionals
We've got you covered with Services from concept to commissioning and Products from panel to the point of interconnect.
>
Project Type: CAISO meter replacements
Alta Wind 4 & 5 – Owned by Clearway Energy
Alta Wind 8 – Owned by Brookfield
Alta Wind 9 (Now Pinyon Pines II ) – Owned by BHE Renewables
Alta Wind 4 – CAISO meter replacement – 150 MW
Alta Wind 5 – Meter replacement – 150 MW
Alta Wind 8 – CAISO meter replacement – 150 MW
Alta Wind 9 – CAISO meter replacement- 150 MW
French Meadows – Meter replacement- 150 MW
Location: Various locations in California
Products/Services: Revenue meters at all locations
Trimark replaced the CAISO-certified revenue metering for each of the sites with the three separate resource owners. All four sites communicate through peer-to-peer functioning. Trimark worked with a third party programmer to program and install main and back-up meters at each of the wind sites.

Customers can receive alerts if an outage occurs and view details to expedite mitigation. Trimark Associates, Inc., the industry leader…
First Resources in Edwards/Sanborn Project Reach Commercial Operation. Folsom, CA, January 4, 2022 – The first four phases of the…
Trimark is pleased to announce that Colin Tepfer has joined the company as Director of Training and Education. Colin is responsible…
Trimark now supports third-party Remote Intelligent Gateways (RIGs) including the SEL RTAC and NovaTech Orion through the Trimark Operations Center….
February 3, 2026 — Trimark is pleased to announce that the United States Patent and Trademark Office has officially granted…
Troubleshooting issues and correcting problems that arise in operating critical infrastructure is a demanding job – everything is high priority….
Project Type: PV rated at 10.5 MW (Aggregated) Location: Richmond, CA EPC: Cenergy Power Products/Services: SCADA, revenue meters, MET stations,…
Project Type: PV generating facilities rated at 3 MW each Location: Palmdale/Lancaster, CA Client/EPC: Swinerton Products/Services: Trimark’s end-to-end solution for…
Project Type: 105MW PV, 20MW/80MWh BESS Location: Rosamond, CA Client/EPC: Matrix Renewables Products/Services: Trimark SCADA including Vantage, Trimark Remote Intelligent…
Project Type: Wind 27.392 MW Location: Mojave, CA Client: Terra-Gen Products/Services: CAISO revenue meters and ARIG configuration Ridgetop II is…