Trimark Commissions Controls for Luna BESS
Aug 04, 2022
Intelligent Battery Control Supports Grid Stability Folsom, CA, August 4, 2022 – Trimark Associates, Inc., the industry leader in intelligent…
Project Type: 15MW Point-of-Delivery (POD) PV/BESS Hybrid Resource composed of 15MW PV, 7MW/14MWh BESS
Location: Taos, NM
Client/EPC: Torch Clean Energy
Trimark delivered Vantage™ SCADA controls for the Taos Mesa Energy Facility in New Mexico. It is the first PV+BESS resource control solution to fully comply with the Modular Energy System Architecture Distributed Energy Resource (MESA-DER) open standard. The “hybrid” site controller manages a 15 MWac solar photovoltaic (PV) array along with a 12 MWac / 24 MWh (2 hour) Tesla battery system.
Trimark will exhibit at the RE+ conference, September 10-12, 2024 in the Anaheim Convention Center. Trimark’s will be at booth…
Trimark’s Experts Weigh in on Separating Retail and Wholesale Meter Data for Battery Energy Storage Systems (BESS) The rapid increase…
Trimark’s System Supports Centralized Control and Cyber Security Best Practices Trimark Associates, Inc., the industry leader in intelligent renewable energy…
Installed 1,043 advanced energy meters to track energy usage throughout Northern Virginia, Washington D.C., and Maryland. Work involved 14 separate…
Project Type: PV generating facility rated at 100 MW Location: Los Angeles County, CA Client/EPC: Cupertino Electric Owner: sPower Products/Services:…