Edwards Sanborn

SBES

Project Type: 810MW AC Hybrid Site (Solar + BESS) comprised of seven separate resouces
Location: Mojave, CA
Client/EPC: Terra-Gen

Trimark delivered and commissioned plant controls for all resources in Edwards-Sanborn Phase 1A – the world’s largest capacity solar-plus-storage project. The seven resources included in the Mojave-based Phase 1A have a nameplate capacity of 810 MW (LGIA limit of 634 MW).

Each resource is managed by Trimark’s intelligent power plant controller (PPC), a utility-scale SCADA system designed to optimize the profitability of photovoltaic (PV) and battery energy storage system (BESS) resources that participate in California’s open energy markets.

To maximize output and support stable power at the point of deliver, each resource’s PPC considers the losses introduced by any of the five hybrid (PV+BESS) and/or two BESS resources. Trimark’s Dynamic Loss Compensator (DLC) calculates energy losses for each resource and applies the value as a control point to the affiliated PPC. Each PPC then adjusts generation, charge and discharge decisions in real time to ensure that its resource delivers the maximum power allowed by the LGIA or the ISO’s target value.

Trimark News

ALERT — SQMD Plan Affirmations Due to CAISO October 31

Aug 29, 2023

Experts say, “Don’t wait to ask for help” Folsom, CA, August 29, 2023 – If your resource participated in the…

Learn More

Trimark Promotes Tom Short to Vice President of Consulting and Client Relations

Apr 04, 2023

Folsom, CA, March 30, 2023 – Trimark Associates, Inc., the industry leader in intelligent energy control, advanced metering, and regulatory…

Learn More

Trimark Adds Texas Office to Serve Growing, Green-Energy Market

Aug 09, 2022

Solar Power Generation is Booming in Texas. Trimark is Committed to Help. Folsom, CA, August 8, 2022 – Trimark Associates,…

Learn More

Trimark’s Domestic Content Documentation Supports IRA Tax Bonus Claims

Jan 02, 2024

Trimark has a long history of buying devices that are manufactured in the U.S. So when the Inflation Reduction Act…

Learn More

Trimark Promotes Tom Short to Vice President of Consulting and Client Relations

Apr 04, 2023

Folsom, CA, March 30, 2023 – Trimark Associates, Inc., the industry leader in intelligent energy control, advanced metering, and regulatory…

Learn More

Trimark’s Expert Voices

Dec 12, 2023

Vince Brashear, P.E., Director of Design and Engineering “The systems we design are a small, but critical, part of power…

Learn More

Projects

Example Projects

Take a minute to see how Trimark has helped resource owners, EPCs, and ISOs change the electric grid.
View All Projects
green-beanworks-b-c-and-d

Green Beanworks: B, C, and D

Jan 10, 2020

Project Type: PV generating facilities rated at 3 MW each Location: Palmdale/Lancaster, CA Client/EPC: Swinerton Products/Services: Trimark’s end-to-end solution for…

Learn More
network-drop-interior

Antelope DSR3

Jan 28, 2020

Project Type: PV generating facility rated at 20 MW Location: Los Angeles County, CA Client/EPC: Cupertino Electric/sPower Products/Services: Trimark provided…

Learn More
sPower Solar Portfolio

AES Solar Portfolio

Jan 04, 2019

Location: 28 Projects throughout the United States EPC: Multiple EPCs including Swinerton Renewable Energy, Rosendin Electric, Signal Energy, Cupertino Electric,…

Learn More
Midway II

Midway II

Dec 03, 2018

Project Type: PV rated at 30 MW Location: Near Calipatria, CA in the Imperial Valley EPC: Blattner Energy Products/Services: SCADA,…

Learn More

Ready. Set.

Letʼs go!

Need a SCADA system that optimizes revenue?
Need help meeting interconnection requirements?
Want to stay in the market and avoid fines?

Weʼve got you!

Get Started Today