Project Type: 810MW AC Hybrid Site (Solar + BESS) comprised of seven separate resouces
Location: Mojave, CA
Client/EPC: Terra-Gen

Trimark delivered and commissioned plant controls for all resources in Edwards-Sanborn Phase 1A – the world’s largest capacity solar-plus-storage project. The seven resources included in the Mojave-based Phase 1A have a nameplate capacity of 810 MW (LGIA limit of 634 MW).

Each resource is managed by Trimark’s intelligent power plant controller (PPC), a utility-scale SCADA system designed to optimize the profitability of photovoltaic (PV) and battery energy storage system (BESS) resources that participate in California’s open energy markets.

To maximize output and support stable power at the point of deliver, each resource’s PPC considers the losses introduced by any of the five hybrid (PV+BESS) and/or two BESS resources. Trimark’s Dynamic Loss Compensator (DLC) calculates energy losses for each resource and applies the value as a control point to the affiliated PPC. Each PPC then adjusts generation, charge and discharge decisions in real time to ensure that its resource delivers the maximum power allowed by the LGIA or the ISO’s target value.

Trimark News

25-Years of Innovative Solutions for Electric Power Infrastructure

Mar 28, 2025

Trimark Associates, Inc. is celebrating 25 years of success in delivering solutions that utility-scale electric power resources require to control…

Learn More
Trimark Finalizes Controls for Phase 1A of World’s Largest PV+BESS Project

Trimark Awarded SCADA for World’s Largest PV+BESS Project

Feb 17, 2021

The Edwards & Sanborn project redefines the utility-scale PV+Storage landscape. Folsom, CA, February 17, 2021 – Trimark Associates, Inc. is…

Learn More

Trimark’s Domestic Content Documentation Supports IRA Tax Bonus Claims

Jan 02, 2024

Trimark has a long history of buying devices that are manufactured in the U.S. So when the Inflation Reduction Act…

Learn More

ALERT — SQMD Plan Affirmations Due to CAISO October 31

Aug 29, 2023

Experts say, “Don’t wait to ask for help” Folsom, CA, August 29, 2023 – If your resource participated in the…

Learn More

Trimark Now Supports SEL RTAC and NovaTech Orion RIGs in CAISO Market

Feb 01, 2024

Trimark now supports third-party Remote Intelligent Gateways (RIGs) including the SEL RTAC and NovaTech Orion through the Trimark Operations Center….

Learn More
Trimark On-Premise Controller Meets NERC-CIP Requirements

Trimark Announces Realtime Monitoring of CAISO RIGs

Jul 06, 2022

Customers can receive alerts if an outage occurs and view details to expedite mitigation. Trimark Associates, Inc., the industry leader…

Learn More

Projects

Example Projects

Take a minute to see how Trimark has helped resource owners, EPCs, and ISOs change the electric grid.
View All Projects
TOC

Clearway Energy Multi-Site Maintenance Service Agreements

Jan 29, 2020

Project Type: PV generating facilities and wind generating facilities – 21 sites Location: CA; one site in AZ Client/EPC: NRG…

Learn More

Townsite Solar

Jun 26, 2023

Project Type: 180 MW Point-of-Delivery (POD) PV/BESS Hybrid Resource composed of 230MW PV, 90MW/360MWh BESS Location: Boulder City, NV Client/EPC:…

Learn More
Cement City

Cement City

Jun 26, 2023

Project Type: 22 MW PV Location: Cement City, MI Client/EPC: AES Products/Services: Trimark SCADA, Trimark Historian, Revenue Meter, MET Stations,…

Learn More

Mulligan

Jun 26, 2023

Project Type: 70 MW Solar AC Coupled Location: Logan County, Illinois Client/EPC: APEX Clean Energy Products/Services: Trimark SCADA including Vantage,…

Learn More

Ready. Set.

Letʼs go!

Need a SCADA system that optimizes revenue?
Need help meeting interconnection requirements?
Want to stay in the market and avoid fines?

Weʼve got you!

Get Started Today