Lancaster Area Battery (LAB)

Project Type: 127 MW AC coupled BESS
Location: Lancaster, CA
Client/EPC: AES

Products/Services: MPPC Modifications, Vantage User interface Configuration and Hosting, NERC – CIP, Integration of BESS Controls with MPPC and CAISO ADS, and Networking.

Trimark worked with AES on the Lancaster Area Battery (LAB) BESS Project, rated at 127 MW AC, to help AES reach their primary project goal of making the solar energy generated in this project a dispatchable renewable energy resource, and adding additional clean energy available to its end user customers into their Renewable portfolio. With the utilization of Trimark’s services, such as MPPC Modifications, Vantage Configuration and Hosting, NERC – CIP, Integration of BESS Controls

Trimark News

Energix Renewables Partners with Trimark to Deliver Portfolio-Wide Ignition SCADA on RTAC

Dec 16, 2022

Trimark Associates, Inc. (Trimark), the industry leader in intelligent energy control, has entered a technology partnership with Energix Renewables to…

Learn More

Trimark’s Domestic Content Documentation Supports IRA Tax Bonus Claims

Jan 02, 2024

Trimark has a long history of buying devices that are manufactured in the U.S. So when the Inflation Reduction Act…

Learn More
Trimark Finalizes Controls for Phase 1A of World’s Largest PV+BESS Project

Trimark Awarded SCADA for World’s Largest PV+BESS Project

Feb 17, 2021

The Edwards & Sanborn project redefines the utility-scale PV+Storage landscape. Folsom, CA, February 17, 2021 – Trimark Associates, Inc. is…

Learn More
Trimark Commissions Controls for Luna BESS

Trimark Commissions Controls for Luna BESS

Aug 04, 2022

Intelligent Battery Control Supports Grid Stability Folsom, CA, August 4, 2022 – Trimark Associates, Inc., the industry leader in intelligent…

Learn More

Trimark Guides AES’ Raceway and Estrella PV+BESS Resources Through SCE’s New Interconnection Testing Protocol

Mar 29, 2024

Trimark Associates, Inc. (Trimark) successfully completed pilot testing for the first resources to pass Southern California Edison’s (SCE) strict, new,…

Learn More

ALERT — SQMD Plan Affirmations Due to CAISO October 31

Aug 29, 2023

Experts say, “Don’t wait to ask for help” Folsom, CA, August 29, 2023 – If your resource participated in the…

Learn More

Projects

Example Projects

Take a minute to see how Trimark has helped resource owners, EPCs, and ISOs change the electric grid.
View All Projects
CAISO-RIG

Ellwood Station

Jan 29, 2020

Project Type: Remote Intelligent Gateway (RIG) relocation Location: Oxnard, CA Client/EPC: GenOn Energy Products/Services: Trimark made configuration changes to an…

Learn More
Corazon-Ranch-Block

Corazon Ranch Solar (Under Construction)

Feb 03, 2021

Project Type: 200 MW PV Location: Laredo, Texas Client/EPC: Worley (project owned by BayWa r.e.) Products/Services: Trimark provided a full…

Learn More
green-beanworks-b-c-and-d

Green Beanworks: B, C, and D

Jan 10, 2020

Project Type: PV generating facilities rated at 3 MW each Location: Palmdale/Lancaster, CA Client/EPC: Swinerton Products/Services: Trimark’s end-to-end solution for…

Learn More
Midway I

Midway I

Dec 05, 2018

Project Type: PV rated at 50 MW Location: Near Calipatria, CA in the Imperial Valley EPC: Blattner Energy Products/Services: SCADA,…

Learn More

Ready. Set.

Letʼs go!

Need a SCADA system that optimizes revenue?
Need help meeting interconnection requirements?
Want to stay in the market and avoid fines?

Weʼve got you!

Get Started Today