Trimark Commissions Controls for Luna BESS

Trimark Commissions Controls for Luna BESS

Intelligent Battery Control Supports Grid Stability

Folsom, CA, August 4, 2022 – Trimark Associates, Inc., the industry leader in intelligent energy control, today announced that it has commissioned plant controls for the Luna Battery Energy Storage System (BESS). Trimark’s Vantage™ SCADA works in cooperation with the Fluence battery controller to manage the 100MW/400MWh BESS and support stable power delivery.

The Challenge

In California’s Antelope Valley, the Big Sky and Big Sky North substations consolidate more than 700 MW of power generation from over 21 utility-scale photovoltaic (PV) resources spread across 60 square miles of high desert.

In this generating environment, Luna BESS is used to support power stability by addressing the challenges of variable irradiance and curtailment. When clouds cross the arrays, Luna BESS can be discharged to support consistent power at the point of delivery (POI). BESS discharges can also be scheduled to extend the time of day that renewable power can be delivered.

The Solution

As a key component of their renewable energy strategy, the Clean Power Alliance (CPA) commissioned the Luna BESS – a utility-scale battery valued at over $100 million. CPA is a Community Choice Aggregator that serves about one million customer accounts in Los Angeles County.

AES Clean Energy developed the grid-connected battery and will manage the resource. Fluence provided the battery system and acted as the EPC.

Trimark’s Vantage™ SCADA receives, validates, and executes ADS setpoints generated by CAISO. Simultaniously, the system works to maintain Voltage at the POI, as required by Southern California Edison’s Grid Code. To meet these requirements, Trimark’s Power Plant Controller measures power values at the POI, then sends real and reactive power setpoint commands to the Fluence BESS controller. Ongoing measurements and set point adjustments are made to maintain the target values.

About Trimark

Trimark Associates, Inc. (Trimark) delivers industry-leading solutions to allow real-time operational control, enable informed management of power production operations, and support regulatory compliance. Trimark’s turnkey products, engineering, and customer support services control, measure, and manage all aspects of power production that utility-scale power producers require to maintain peak business performance.

Trimark News

Landis+Gyr Revenue Meters No Longer CAISO Approved

Oct 16, 2023

According to CAISO, Landis+Gyr meters are no longer approved for new or replacement installations at CAISO-metered entities. The change was…

Learn More

Trimark Announces Realtime Monitoring of CAISO RIGs

Jul 06, 2022

Customers can receive alerts if an outage occurs and view details to expedite mitigation. Trimark Associates, Inc., the industry leader…

Learn More

25-Years of Innovative Solutions for Electric Power Infrastructure

Mar 28, 2025

Trimark Associates, Inc. is celebrating 25 years of success in delivering solutions that utility-scale electric power resources require to control…

Learn More

ALERT — SQMD Plan Affirmations Due to CAISO October 31

Aug 29, 2023

Experts say, “Don’t wait to ask for help” Folsom, CA, August 29, 2023 – If your resource participated in the…

Learn More

Trimark Adds Texas Office to Serve Growing, Green-Energy Market

Aug 09, 2022

Solar Power Generation is Booming in Texas. Trimark is Committed to Help. Folsom, CA, August 8, 2022 – Trimark Associates,…

Learn More

RTAC Q&A with Trimark’s Dean Fagan

Jan 25, 2022

Dean Fagan, Director of SCADA Integration at Trimark Associates, has over 24 years of experience in planning, implementing, and supporting…

Learn More

Projects

Example Projects

Take a minute to see how Trimark has helped resource owners, EPCs, and ISOs change the electric grid.
View All Projects

Ellwood Station

Jan 29, 2020

Project Type: Remote Intelligent Gateway (RIG) relocation Location: Oxnard, CA Client/EPC: GenOn Energy Products/Services: Trimark made configuration changes to an…

Learn More

Beacon Solar

Jan 05, 2019

Project Type: PV rated at 152 MW combined Location: California City, California Client: Rosendin Electric Products and Services: SCADA, meter,…

Learn More

Summer and Winter Wheat

Jan 06, 2019

Project Type: 2 Co-located PV sites rated at 20 MW (Summer) & 1.5 MW (Winter) Location: San Joaquin, CA EPC:…

Learn More

Longroad Energy Multi-Site Maintenance and Data Management Service Agreements

Jan 28, 2020

Project Type: PV generating facilities – over 50 sites Location: CA and MA Client/EPC: N/A Products/Services: Multi-year service agreement with…

Learn More