Trimark Contracted for SCADA and NRI Services for Gaskell 2-5 PV+BESS
Apr 18, 2022
Trimark Associates, Inc., the industry leader in intelligent energy management, has been awarded a contract to provide integrated SCADA, complex…
Expert insight helps lower your risk and reduce costs -- a direct benefit to your bottom line.
Better for the Owner! Better for the Integrator! Better for the Grid!
End-to-end guidance from experts who have guided over 900 resources to successful grid connection.
The Trimark Operations Center (TOC) helps you maintain compliance and ensure accurate data.
A Comprehensive Training Ecosystem for Power Industry Professionals
Trimarkl's OCC delivers NERC-compliant monitoring, alarm response, dispatch, and failover capabilities.
We've got you covered with Services from concept to commissioning and Products from panel to the point of interconnect.
Getting through CAISO new resource implementation takes more than just ticking off paperwork. You have to know the timing, schedules, and how systems work together. Even a simple mistake or missed deadline may lead to weeks of delay which can push your project down the cue of projects awaiting approval. That is why late October is the perfect time to check everything twice.
Projects set to go live in winter need extra stability. Weather can turn fast and limited access to equipment can hold up fixes. If your site is still chasing basic tests in November or December, you could end up losing daylight waiting for the next work window. Doing your checks and updates now keeps your project on track and leaves you with more time to catch any problems before they matter.
Part of preparing a site to join the market includes following CAISO’s New Resource Implementation (NRI) process to ensure that all forms, required equipment, and point-to-point tests are completed ahead of time. Every part of the system—SCADA, meters, telecom lines, and device controls—must match the standards and logic set by CAISO. The process is meant to organize data and checks so the site is ready for market participation.
Schedules are tight. Once your project is accepted into the CAISO queue, every stage comes with deadlines for reviews and tasks. Late submissions or incomplete packages mean lost time and rework.
The process is a team effort. Developers, EPCs, utility staff, CAISO compliance reviewers, and integration vendors are each responsible for a piece of the project. If even one link slips, the entire process waits. Allowing space for each role to get their job done helps maintain the schedule and quality.
Trimark Associates, Inc. delivers CAISO new resource implementation, including market registration help, metering, telemetry, and SCADA integration, keeping new projects aligned through all compliance and testing phases.
Most hold-ups are related to missed handoffs or slow scheduling. Acquiring an ECN from AT&T can be a long-lead item. Procuring, installation, validation and testing must all occur before the critical point-to-point test to avoid stalling progress. Data must be visible to CAISO or it does not count.
Metering is another spot where projects get tripped up. Missing as-builts, incorrect device settings, wiring errors, or a forgotten serial number can all result in holds. CAISO checks each test point and compares the documented plan against what is built. The Trimark metering team ensures that the entire solution meets CAISO requirements defined in the tariff and business practices manual.
Alignment across project partners is key. Developers, EPCs, and SCADA providers must all stay in sync. If integration tests and field notes do not match, the whole site could get sent back for corrections and retesting. Clear status sharing and document review reduce the number of costly surprises as you get closer to go-live.
A good schedule is more than a list of due dates. Each step should map to a CAISO handoff, spelling out who submits what, when, and how that wraps into the next step. Avoid general or one-size-fits-all plans—instead, track every project handoff individually.
Keep documents living, not static. Build and edit drafts that reflect exactly what is on site as changes occur — not a 90 percent plan. Synchronized records support accurate, timely and successful field commissioning while complying with CAISO requirements.
Telemetry deserves extra attention. Every measurement, relay, and point should match CAISO’s naming and reporting logic. Double-check what your SCADA system sends and ensure it matches what the meter reads. Gaps in this chain are a leading cause of late project holds, and they are best fixed now.
Early planning for CAISO new resource implementation lays the foundation for smooth, reliable operations. Teams that keep everything aligned—hardware, paperwork, integration logic—face fewer surprises, can spot and fix issues calmly, and handle transitions without panic.
Good documentation, clear status, and signal checks give everyone from field crews to operations a direct path. Instead of last-minute scrambles, the project keeps moving forward naturally. When your setup is solid, adjustments are fast, testing is simpler, and that edge carries through to dependable market participation. That is the benefit of strong fall preparation.
If your project is facing delays in documentation or scheduling hiccups before winter hits full stride, you’re not the only one. Teams often run into issues during handoffs or late-season weather shifts, which can push commissioning farther out than expected. Getting ahead of those problems now can save time later. If you’re entering the queue soon, take a few minutes to review our steps for a smooth and timely CAISO new resource implementation. Trimark Associates, Inc. is here to help—reach out when you’re ready to connect.
Trimark Associates, Inc., the industry leader in intelligent energy management, has been awarded a contract to provide integrated SCADA, complex…
Trimark has some big things to share at RE+ in Las Vegas, November 16-19, 2026. Come visit Trimark in Booth…
According to CAISO, Landis+Gyr meters are no longer approved for new or replacement installations at CAISO-metered entities. The change was…
Trimark Associates is pleased to announce the promotion of Zack Lemley to Manager of Engineering and Design. This advancement reflects…
Controller to Lead Trimark Accounting Team and Processes Folsom, CA, April 28, 2023 – Trimark Associates, Inc. (Trimark), the industry…
Troubleshooting issues and correcting problems that arise in operating critical infrastructure is a demanding job – everything is high priority….
Project Type: PV rated at 75 MW Location: Mecca, CA under Imperial Irrigation District (IID) utility EPC: Sunpin Solar Products/Services:…
Project Type: PV rated at 50 MW Location: Near Calipatria, CA in the Imperial Valley EPC: Blattner Energy Products/Services: SCADA,…
Project Type: PV rated at 50 MW Location: Near Calipatria, CA in the Imperial Valley EPC: Blattner Energy Products/Services: SCADA,…
Project Type: 810MW AC Hybrid Site (Solar + BESS) comprised of seven separate resouces Location: Mojave, CA Client/EPC: Terra-Gen Trimark…
Need a SCADA system that optimizes revenue? Need help meeting interconnection requirements? Want to stay in the market and avoid fines? Weʼve got you!