Southampton Solar

Southampton Solar

Southampton-Solar-20171004_102807_002Project Type: PV rated at 100 MW

Location: Franklin, VA in Southampton County

EPC: Signal Energy

Products/Services: SCADA, MET stations

Designed by Westwood, the site included 42 TMEIC 2500kW inverters and a NEXTracker solar tracking system. Southampton Solar was brought to COD by Signal Energy for Dominion Energy. Signal Energy was the EPC responsible for managing construction. Signal Energy contracted Trimark to deliver Trimark SCADA to support PV plant operations, regulate electric power generation and stabilize power at the point of interconnection. Trimark also designed and installed 6 meteorological weather station as well as 30 remote wind stations.

Trimark News

Trimark Commissions Controls for Luna BESS

Trimark Commissions Controls for Luna BESS

Aug 04, 2022

Intelligent Battery Control Supports Grid Stability Folsom, CA, August 4, 2022 – Trimark Associates, Inc., the industry leader in intelligent…

Learn More

Trimark Guides AES’ Raceway and Estrella PV+BESS Resources Through SCE’s New Interconnection Testing Protocol

Mar 29, 2024

Trimark Associates, Inc. (Trimark) successfully completed pilot testing for the first resources to pass Southern California Edison’s (SCE) strict, new,…

Learn More

Trimark On-Premise Controller Meets NERC-CIP Requirements

Aug 01, 2022

Trimark’s System Supports Centralized Control and Cyber Security Best Practices Trimark Associates, Inc., the industry leader in intelligent renewable energy…

Learn More

Trimark Guides AES’ Raceway and Estrella PV+BESS Resources Through SCE’s New Interconnection Testing Protocol

Mar 29, 2024

Trimark Associates, Inc. (Trimark) successfully completed pilot testing for the first resources to pass Southern California Edison’s (SCE) strict, new,…

Learn More

Trimark Names John Renfroe as Vice President of Software Engineering

Mar 20, 2023

New VP to Lead Strategic Direction for Software and Technology Folsom, CA, March 21, 2023 – Trimark Associates, Inc., the…

Learn More
RIG-Blog-Thumbnail

CAISO to Discontinue TLS 1.0/1.1 Support for RIGs

Apr 13, 2021

To our valued clients, You may have recently seen the following email from CAISO: You are receiving this notice as…

Learn More

Projects

Example Projects

Take a minute to see how Trimark has helped resource owners, EPCs, and ISOs change the electric grid.
View All Projects
Big Sky North Substation

Big Sky North Substation

Jan 10, 2019

Big Sky North Project Type: PV rated at 105 MW Location: Lancaster, CA in LA County EPC: Rosendin Electric, Inc….

Learn More

Pullman

Jun 26, 2023

Project Type: 22 MW PV Location: Pullman, MI Client/EPC: AES Products/Services: Trimark SCADA, Trimark Historian, Revenue Meter, MET Station, Network…

Learn More
SBES

Edwards Sanborn

Jun 26, 2023

Project Type: 810MW AC Hybrid Site (Solar + BESS) comprised of seven separate resouces Location: Mojave, CA Client/EPC: Terra-Gen Trimark…

Learn More
DCIM

Taos Mesa Energy Center

Jun 26, 2023

Project Type: 15MW Point-of-Delivery (POD) PV/BESS Hybrid Resource composed of 15MW PV, 7MW/14MWh BESS Location: Taos, NM Client/EPC: Torch Clean…

Learn More

Ready. Set.

Letʼs go!

Need a SCADA system that optimizes revenue?
Need help meeting interconnection requirements?
Want to stay in the market and avoid fines?

Weʼve got you!

Get Started Today