Project Type: 100 MW PV (Part of Grand Central cluster)
Location: Eloy, AZ
Client/EPC: AES
Products/Services: Trimark SCADA Systems Integration and Network Drops.
The West Line project consisted of a 100 MW AC solar project located on private lands in City of Coolidge and Pinal County, Arizona. This Project interconnected to Pinal West 230kV substation via approximately 1.2 miles of underground 230kV running north/south between the eastern edge of county pavement and west of the ED2 MV distribution overhead lines. Trimark assisted AES in this project by providing Trimark SCADA Systems Integration along with 30 Network Drops included with patch panels.
Trimark has announced organizational changes and promotions to bolster the company’s commitment to service excellence. “Rapid market growth in the…
Trimark is pleased to announce that we will be exhibiting at the Cleanpower Conference and Exhibition in Phoenix, Arizona, May…
Trimark is proud to design and manufacture mission-critical systems used to operate electric power generation resources. “Our systems are built…
Project Type: PV rated at 3.75 Location: Lancaster, California Client: SolarCity Products and Services: Revenue meter, RIG, SCADA, MET station,…
Project Type: PV rated at 152 MW combined Location: California City, California Client: Rosendin Electric Products and Services: SCADA, meter,…