Trimark Commissions Controls for Luna BESS

Trimark Commissions Controls for Luna BESS

Intelligent Battery Control Supports Grid Stability

Folsom, CA, August 4, 2022 – Trimark Associates, Inc., the industry leader in intelligent energy control, today announced that it has commissioned plant controls for the Luna Battery Energy Storage System (BESS). Trimark’s Vantage™ SCADA works in cooperation with the Fluence battery controller to manage the 100MW/400MWh BESS and support stable power delivery.

The Challenge

In California’s Antelope Valley, the Big Sky and Big Sky North substations consolidate more than 700 MW of power generation from over 21 utility-scale photovoltaic (PV) resources spread across 60 square miles of high desert.

In this generating environment, Luna BESS is used to support power stability by addressing the challenges of variable irradiance and curtailment. When clouds cross the arrays, Luna BESS can be discharged to support consistent power at the point of delivery (POI). BESS discharges can also be scheduled to extend the time of day that renewable power can be delivered.

The Solution

As a key component of their renewable energy strategy, the Clean Power Alliance (CPA) commissioned the Luna BESS – a utility-scale battery valued at over $100 million. CPA is a Community Choice Aggregator that serves about one million customer accounts in Los Angeles County.

AES Clean Energy developed the grid-connected battery and will manage the resource. Fluence provided the battery system and acted as the EPC.

Trimark’s Vantage™ SCADA receives, validates, and executes ADS setpoints generated by CAISO. Simultaniously, the system works to maintain Voltage at the POI, as required by Southern California Edison’s Grid Code. To meet these requirements, Trimark’s Power Plant Controller measures power values at the POI, then sends real and reactive power setpoint commands to the Fluence BESS controller. Ongoing measurements and set point adjustments are made to maintain the target values.

About Trimark

Trimark Associates, Inc. (Trimark) delivers industry-leading solutions to allow real-time operational control, enable informed management of power production operations, and support regulatory compliance. Trimark’s turnkey products, engineering, and customer support services control, measure, and manage all aspects of power production that utility-scale power producers require to maintain peak business performance.

Trimark News

Names Rajinita Haumschilt

Trimark Names Rajinita Haumschilt as Financial Controller

Apr 28, 2023

Controller to Lead Trimark Accounting Team and Processes Folsom, CA, April 28, 2023 – Trimark Associates, Inc. (Trimark), the industry…

Learn More

Trimark Adds Texas Office to Serve Growing, Green-Energy Market

Aug 09, 2022

Solar Power Generation is Booming in Texas. Trimark is Committed to Help. Folsom, CA, August 8, 2022 – Trimark Associates,…

Learn More
trimark-awarded-service-agreement

Trimark Awarded Service Agreement for Clearway Energy’s Utility-Scale PV Sites

Jun 26, 2019

Providing CAISO Remote Intelligent Gateway and Revenue Meter Monitoring and Maintenance Services Folsom, CA, June 26, 2019 – Trimark Associates,…

Learn More
Trimark On-Premise Controller Meets NERC-CIP Requirements

Trimark Announces Realtime Monitoring of CAISO RIGs

Jul 06, 2022

Customers can receive alerts if an outage occurs and view details to expedite mitigation. Trimark Associates, Inc., the industry leader…

Learn More

Meeting CAISO Rules for BESS Metering

Feb 26, 2024

Trimark’s Experts Weigh in on Separating Retail and Wholesale Meter Data for Battery Energy Storage Systems (BESS) The rapid increase…

Learn More

Cloud-Based ADS Supports Participation in Ancillary Services Market

Oct 06, 2023

Folsom, CA, October 6, 2023 – Trimark has introduced cloud-based, Automatic Dispatch System (ADS) services to help small BESS and…

Learn More

Projects

Example Projects

Take a minute to see how Trimark has helped resource owners, EPCs, and ISOs change the electric grid.
View All Projects
Chevron

Chevron 2 and 8.5

Jan 22, 2019

Project Type: PV rated at 10.5 MW (Aggregated) Location: Richmond, CA EPC: Cenergy Power Products/Services: SCADA, revenue meters, MET stations,…

Learn More

Lawai PV and Storage

Jan 29, 2020

Project Type: PV generation rated at 28 MW plus 100 MWh/five hour energy storage facility Location: Between Lawai and Koloa…

Learn More

Colgreen North Shore

Jan 06, 2019

Project Type:  PV rated at 75 MW Location: Mecca, CA under Imperial Irrigation District (IID) utility EPC: Sunpin Solar Products/Services:…

Learn More

Lawai PV and Storage

Jan 29, 2020

Project Type: PV generation rated at 28 MW plus 100 MWh/five hour energy storage facility Location: Between Lawai and Koloa…

Learn More

Ready. Set.

Letʼs go!

Need a SCADA system that optimizes revenue?
Need help meeting interconnection requirements?
Want to stay in the market and avoid fines?

Weʼve got you!

Get Started Today