Trimark Commissions Controls for Luna BESS

Trimark Commissions Controls for Luna BESS

Intelligent Battery Control Supports Grid Stability

Folsom, CA, August 4, 2022 – Trimark Associates, Inc., the industry leader in intelligent energy control, today announced that it has commissioned plant controls for the Luna Battery Energy Storage System (BESS). Trimark’s Vantage™ SCADA works in cooperation with the Fluence battery controller to manage the 100MW/400MWh BESS and support stable power delivery.

The Challenge

In California’s Antelope Valley, the Big Sky and Big Sky North substations consolidate more than 700 MW of power generation from over 21 utility-scale photovoltaic (PV) resources spread across 60 square miles of high desert.

In this generating environment, Luna BESS is used to support power stability by addressing the challenges of variable irradiance and curtailment. When clouds cross the arrays, Luna BESS can be discharged to support consistent power at the point of delivery (POI). BESS discharges can also be scheduled to extend the time of day that renewable power can be delivered.

The Solution

As a key component of their renewable energy strategy, the Clean Power Alliance (CPA) commissioned the Luna BESS – a utility-scale battery valued at over $100 million. CPA is a Community Choice Aggregator that serves about one million customer accounts in Los Angeles County.

AES Clean Energy developed the grid-connected battery and will manage the resource. Fluence provided the battery system and acted as the EPC.

Trimark’s Vantage™ SCADA receives, validates, and executes ADS setpoints generated by CAISO. Simultaniously, the system works to maintain Voltage at the POI, as required by Southern California Edison’s Grid Code. To meet these requirements, Trimark’s Power Plant Controller measures power values at the POI, then sends real and reactive power setpoint commands to the Fluence BESS controller. Ongoing measurements and set point adjustments are made to maintain the target values.

About Trimark

Trimark Associates, Inc. (Trimark) delivers industry-leading solutions to allow real-time operational control, enable informed management of power production operations, and support regulatory compliance. Trimark’s turnkey products, engineering, and customer support services control, measure, and manage all aspects of power production that utility-scale power producers require to maintain peak business performance.

Trimark News

Trimark to Exhibit at Cleanpower 2024 in Minneapolis

Feb 22, 2024

Trimark will exhibit at the Cleanpower Conference and Exhibition, May 7-9, 2024 in the Minneapolis Convention Center. You can find…

Learn More

25-Years of Innovative Solutions for Electric Power Infrastructure

Mar 28, 2025

Trimark Associates, Inc. is celebrating 25 years of success in delivering solutions that utility-scale electric power resources require to control…

Learn More

ALERT — SQMD Plan Affirmations Due to CAISO October 31

Aug 29, 2023

Experts say, “Don’t wait to ask for help” Folsom, CA, August 29, 2023 – If your resource participated in the…

Learn More
IMG_3829

Happy National Math Day (and Pi Day Too)

Mar 11, 2022

Ask any electrical engineer for their favorite mathematical formula and you’re likely to hear all about Ohm’s law. It’s an…

Learn More

Trimark On-Premise Controller Meets NERC-CIP Requirements

Aug 01, 2022

Trimark’s System Supports Centralized Control and Cyber Security Best Practices Trimark Associates, Inc., the industry leader in intelligent renewable energy…

Learn More

Trimark Adds Texas Office to Serve Growing, Green-Energy Market

Aug 09, 2022

Solar Power Generation is Booming in Texas. Trimark is Committed to Help. Folsom, CA, August 8, 2022 – Trimark Associates,…

Learn More

Projects

Example Projects

Take a minute to see how Trimark has helped resource owners, EPCs, and ISOs change the electric grid.
View All Projects
SBES

Edwards Sanborn

Jun 26, 2023

Project Type: 810MW AC Hybrid Site (Solar + BESS) comprised of seven separate resouces Location: Mojave, CA Client/EPC: Terra-Gen Trimark…

Learn More
Hawaii Advanced Metering Infrastructure

Hawaii Advanced Metering Infrastructure (AMI)

Jan 08, 2019

Provided, installed and configured 477 advanced energy meters at Pearl Harbor, Island, Smith and Hickam AFBs. Project included configuration, testing,…

Learn More
Garland Solar

Garland Solar

Jan 05, 2019

Project Type: PV rated at 200 MW Location: Kern County, California Client: Signal Energy Constructors Products and Services: SCADA, RIG,…

Learn More

Colgreen North Shore

Jan 06, 2019

Project Type:  PV rated at 75 MW Location: Mecca, CA under Imperial Irrigation District (IID) utility EPC: Sunpin Solar Products/Services:…

Learn More

Ready. Set.

Letʼs go!

Need a SCADA system that optimizes revenue?
Need help meeting interconnection requirements?
Want to stay in the market and avoid fines?

Weʼve got you!

Get Started Today